Description of the Works
Removal and replacement of existing render system, including new expansion joints, localised window interface works, full basecoat and mesh reinforcement, and application of new silicone render finish. Access, protection, and associated preliminaries.
Pre start meeting: 3 July 2026
Works start: 13 July 2026
Works completed: 31 July 2026
How can I get more information and help?
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.
Name and Job Title: Tom Dell – Building Fabric Surveyor
Mobile: 07895 331 871